Connection Process & Requirements
Step 1: Service Availability
Once municipal water or sanitary service is installed at the property line and confirmed live by InnServices, property owners may apply for a Town building permit to connect.
Step 2: Building Permit
A building permit is required prior to connection.
Building Permits - Town of Innisfil
Step 3: Installing the Connection
Water Connection
- Municipal water piping and water meter must be installed in accordance with Town bylaws and engineering standards.
- All fixtures in the home must connect to municipal water.
- Existing wells may be maintained for other uses, but must be fully disconnected from municipal water lines.
- Once connected, contact InnServices to arrange water meter installation.
Sanitary Sewer Connection
- Municipal sanitary piping must meet Town bylaws and engineering standards.
- All sanitary drainage must connect to municipal sewer.
- Existing septic systems must be disconnected and abandoned in accordance with municipal and provincial requirements.
Step 4: Construction Requirements
Installing a new municipal service requires open excavation from the property line to the residence, as well as internal plumbing work, completed by a qualified contractor.
Step 5: Inspection & Activation
Final inspections are completed by the Town of Innisfil. After approval is confirmed, InnServices will install the water meter and activate the service.